The Cape
Chapter Two Footnotes
6555th Aerospace Test Group
The Commander's office and most of the Support Division's people were
located at Patrick Air Force Base. The ATLAS Systems Division and the TITAN
III Systems Division operated out at the Cape's launch facilities approximately
20 miles north of Patrick.
Space Launch
Vehicle Systems Division
The new division was created by joining the ATLAS Mission Management
Branch and ATLAS/AGENA Launch Operations Branch with the TITAN III Systems
Division's Engineering and Launch Operations Branch, the Launch Services
Branch, and the Program Management Branch.
Satellite Systems Division
The Satellite Systems Division had no formal organizational structure
per se, but personnel assigned to various payload programs (e.g., Defense
Support Program, DSCS, FLTSATCOM, GPS, etc.) reported directly to the Division
Chief.
personnel were transferred
The 1st Space Launch Squadron was created from the 6555th's DELTA II
program resources previously assigned to the Medium Launch Vehicle Division.
The 1st was assigned directly to ESMC, and its first commander was Lt.
Colonel R. M. Moyer. The Squadron was authorized 16 officers, 12 enlisted
people and five civilians by the end of December 1991. The remaining portions
of the Medium Launch Vehicle Division became the ATLAS II CTF. The ATLAS
II CTF was directed by Lt. Colonel J. T. Brock, and it was authorized 11
officers, seven enlisted people and four civilians at the end of October
1991. The Space Launch Vehicle Systems Division became the TITAN IV CTF,
and it was directed by Lt. Colonel William H. Barnett. By the end of October
1991, the TITAN IV CTF was authorized approximately 48 officers, 32 enlisted
people and 13 civilians. The Spacecraft Division and the Resource Management
Division (a.k.a. Programs/Analysis Division) continued to operate after
the transfer to AFSPACECOM as "Payload Operations" and "Ops
Resource Management" under Colonel Michael R. Spence in his capacity
as ESMC's Deputy for Launch Operations. Payload Operations was authorized
23 officers, 27 enlisted people and seven civilians in October 1991. During
the same period, Ops Resource Management had authorizations for three officers,
four enlisted people and six civilians.
45th Spacecraft
Operations Squadron
The 45th Spacecraft Operations Squadron's first commander was Lt. Colonel
Ivory J. Morris. The Squadron was authorized 24 officers, 23 enlisted people
and seven civilians by the middle of January 1992.
launch and
spacecraft agency training aids
Training lesson plans existed in the 6555th as far back as the old
LARK and MATADOR programs in the early 1950s, but much of the 6555th's
training program under AFSC was oriented toward apprenticeship (i.e., training
someone by having that person watch another person perform tasks). Our
knowledge of Test Group training is thus largely undocumented. In the interest
of making their new launch resources "operational," AFSPACECOM
insisted on written study guides and operating instructions at the squadron
level (i.e., like other operational commands). Following ESMC's transfer
to AFSPACECOM, the 1st Space Launch Squadron, the CTFs and the Payload
Operations Office began writing the required study guides and operating
instructions.
The
Launch Controller, Anomaly Team Chief and Launch Weather Officer
The Weather Officer was assigned to the 45th Weather Squadron, but
the other officials came from the 1st Space Launch Squadron.
updates from the SLOCs
On launch day, four SLOCs were assigned to supervise the following
operations: 1) white room closeout, tower walkdown and Mobile Service Tower
(MST) rollback, 2) lanyard tensioning, Umbilical Tower walkdown and MST
rollback, 3) launch deck closeout, solid motor arming and MST rollback,
and 4) postlaunch securing and scrub turnaround tasks. In addition to this
supervision, the Squadron's Chief of Operations Flight conducted his own
walkdown of both towers to ensure equipment was properly configured for
the MST rollback.
Johnson Controls World
Services
Johnson Controls acquired the old range support contractor, Pan American
World Services, in February 1989. The company kept the Pan Am logo until
July 1990. Pan American World Services had supported the Eastern Range
(a.k.a., Eastern Test Range) under an unbroken string of contracts since
December 1953.
Aerospace
Systems Division and the Space Launch Systems Division
On 12 June 1990, the ESMC Vice Commander approved the merger of those
two divisions into a new 37-member Heavy Launch Vehicle Division. Nine
personnel were transferred from the Aerospace Systems Division to the Director
of Quality's office and other divisions.
MLV and Payloads Division
As the name suggests, the MLV and Payloads Division was also responsible
for ATLAS and DELTA medium launch vehicle (MLV) quality assurance.
executive
agent for the Space and Missile Systems Center
Systems Program Offices (SPOs) assigned to the Space and Missile Systems
Center "owned" the various spacecraft contracts and exercised
authority over the individual Payload Support Contractors (PSCs), but the
Field Program Manager (FPM) managed individual programs at the Cape and
KSC on behalf of the various SPOs. The reader should note that this relationship
went back to the 6555th Aerospace Test Group, the Space Systems Division
and the Division's predecessor organizations. Space Systems Division became
the Space and Missile Systems Center as a result of the merger of AFSC
and AFLC into Air Force Materiel Command on 1 July 1992. The Space and
Missile Systems Center was headquartered in Los Angeles, California.
one to
two years before a spacecraft arrived
Typically, detailed spacecraft planning and scheduling began 18 months
before launch, but processing requirements might be considered as much
as four years before launch.
Chief
of the 6555th Test Group's TITAN III Systems Division
Lt. Colonel Ansel L. Wood became "Acting Commander" of the
Division after Lt. Colonel Conti transferred to a new assignment at Tinker
Air Force Base, Oklahoma in November 1971. Lt. Colonel Robert D. Woodward
succeeded Lt. Colonel Wood as TITAN III Systems Division Chief in May 1972.
Lt. Colonel Edwin W. Brenner became Chief of the TITAN III Systems Division
after Colonel Woodward assumed command of the 6555th Aerospace Test Group
on 16 July 1973. Woodward's predecessor, Colonel Arthur W. Banister, had
succeeded Colonel Davis P. Parrish as Group Commander on 24 August 1972.
Integrate-Transfer-Launch
(ITL) Area
The ITL consisted of launch complexes 40 and 41, the Vertical Integration
Building (VIB), the Solid Motor Assembly Building (SMAB), the Solid Rocket
Motor Processing Area, offices, warehouse space, railroads and the TITAN
IIIC transporter system. The Solid Rocket Motor Processing Area consisted
of a Missile Inert Storage Building for warehousing and processing solid
rocket motor components, Segment Arrival Storage (SAS) areas, and a Receiving
Inspection Storage (RIS) Building.
Hangar
L and Missile Assembly Buildings I and II
All payload fairing activities at Hangar L were phased out in July
1971, and the building was returned to the Air Force Eastern Test Range
(AFETR) organization. TITAN payload fairing storage and processing operations
shifted to missile assembly buildings I and II following the completion
of modifications to those buildings in July and August 1971. Missile Assembly
Building I (MAB I) was used for payload fairing processing operations (e.g.,
the application of thermal protective coatings, ordnance installation,
mechanical and electrical testings and fairing modifications). Missile
Assembly Building II provided an air-conditioned storage area for flight-ready
payload fairings.
companies' employees
On 1 July 1971, Martin Marietta had 232 people working its TITAN III
operations at the Cape. During the same period, United Technologies had
49 people on the Range, and DELCO and Aerojet had 14 employees apiece.
Aerospace Corporation was represented on the Eastern Test Range with 19
employees. By January 1973, TITAN III Systems Division authorizations had
declined to 18 officers, 31 airmen and 12 civilians and actual manning
dropped to around 60 people. The ratio of contractors to Division personnel
changed to around 6:1 at that time, but it gradually moved back to around
4:1 in later years.
Defense Support Program
(DSP)
According to a synopsis of the DSP program printed in Airman Magazine
in September 1993 (Volume XXXVIII, Number 9), Defense Support Program payloads
were designed to detect missile launches, space launches and nuclear detonations.
From the early 1970s onward, the DSP system provided an uninterrupted early
warning capability, feeding data to NORAD and (later) U.S. Space Command
early warning centers at Cheyenne Mountain, Colorado. The DSP constellation
of satellites orbited approximately 22,000 miles above the Earth and employed
infrared sensors to detect missile and space booster exhaust plumes against
Earth's background. Though the first-generation DSP satellites weighed
approximately 1,800 pounds apiece, the latest DSP spacecraft weighed about
5,000 pounds. The newest DSP satellites measured 32 feet 8 inches long
and 22 feet in diameter. TRW was the prime contractor for DSP spacecraft.
launched
the first two Phase II Defense Satellite Communications Program (DSCP)
satellites
The flight plan called for the injection of the TITAN IIIC's second
stage, transtage and payload into an initial 82 x 108-nautical-mile parking
orbit. The transtage and payload proceeded to a highly elliptical transfer
orbit (e.g., 19,571 nautical miles at its apogee) and a final near synchronous
orbit (19,494 x 19,323 nautical miles) before each of the two 1,130-pound
satellites were injected into their proper orbits. One of the satellites
was placed above the Atlantic Ocean, and the other was positioned over
the Pacific. The Air Force Satellite Control Facility (AFSCF) in Sunnyvale,
California encountered some command problems with the spacecraft initially,
but both satellites were soon functioning normally. The satellites were
built by TRW to meet the military's demand for high capacity, super-high
frequency secure voice and data communications. Each DSCP satellite could
relay as many as 1,300 duplex voice channels in an anti-jamming, secure
voice environment.
TITAN IIIC
vehicles (e.g., C-25 and C-28)
Core vehicles C-28 and C-25 arrived at the Cape on 25 October 1973
and 17 April 1974 respectively. Following their Acceptance CSTs, Launch
Vehicle C-28 was accepted by the Air Force on 18 April 1974, and Launch
Vehicle C-25 was accepted on 27 September 1974. The next core vehicle-C-29-arrived
at the Cape on 24 October 1974. Erection of that vehicle began in the VIB
on 28 October 1974, after C-28 was transferred to a storage stand in Cell
#4 of the VIB. In effect, C-29 bumped C-28 in the launch lineup.
prelaunch
testing after the lightning strikes
In addition to that testing, Stage III propellants and fuel were off-loaded,
and all flight ordnance electrical systems were disconnected and checked
for damage.
command
of the 6555th Aerospace Test Group
During the three-week interval between the two commanders, the 6595th
Aerospace Test Wing Commander (Colonel William C. Chambers) visited the
Cape and assumed temporary command of the 6555th Aerospace Test Group.
Division was merged
The TITAN III Systems Division had 16 officers, 22 airmen and 13 civilians
assigned to its various activities during the summer of 1975, but it lost
Major Jerry H. Freer and his Space Satellite Systems branch to the new
Satellite Systems Division on 1 November 1975. (The Satellite Systems Division
also took over the Satellite Assembly Building in addition to Building
34705, Complex 14's ready building and the north half of Hangar AA.) What
was lost in satellite systems was more than gained back in ATLAS booster
facilities and people under the new division: the new Space Launch Vehicle
Systems Division was authorized 20 officers, 31 airmen and 13 civilians
at the end of 1975, and it had 19 officers, 30 airmen and 13 civilians
assigned to its activities during that period. It also picked up ATLAS/AGENA
facilities on Complex 13.
Launch Vehicle C-30
Launch Vehicle C-30 was mated to its SOLRAD and LES payloads on February
18th and February 25th, and the Launch CST was completed on 7 March 1976.
The countdown for the mission got underway at Complex 40 on March 14th.
Vehicle lift-off occurred at 2025:39 Eastern Standard Time on the 14th,
which was equivalent to 0125:39 Greenwich Mean Time on 15 March 1976.
Lincoln Experimental
Satellites
The Lincoln Experimental Satellites were experimental communications
satellites built for the Air Force by the Massachusetts Institute of Technology.
Each LES was ten feet long and weighed approximately 1,000 pounds. The
satellites were placed in synchronous Earth orbit at an altitude of 22,300
miles to experiment with improved methods for maintaining voice or digital
data circuits among widely separated, fixed or mobile communications terminals.
The circuits were jam-resistant to allow operation in a hostile environment.
SOLRAD 11A and 11B
The SOLRAD spacecraft were built by the Naval Research Laboratory to
monitor solar conditions and forecast disturbances severe enough to affect
long-range communications and navigation systems. Each SOLRAD was 15 inches
in diameter and 58 inches high, and each weighed about 400 pounds.
Eastern Daylight Time
During the 1970s and most of the 1980s, Eastern Daylight Time was used
from 2 a.m. on the last Sunday in April to 2 a.m. on the last Sunday in
October. During that portion of the year, clocks were advanced one hour
ahead of standard time. Thus, Eastern Daylight Time was one hour later
than Eastern Standard Time and four hours earlier than Greenwich Mean Time.
On 8 July 1986, President Reagan signed a bill to move the start of Daylight
Savings Time to the first Sunday in April.
Remote Vehicle
Checkout Facility (RVCF)
The RVCF was an extension of the New Hampshire Tracking Station, and
it was used to determine if commands sent from a remote tracking facility
(in this instance, the New Hampshire Tracking Station) could be received
by a satellite in the RVCF. Other tests in the RVCF also confirmed a satellite's
ability to send telemetry to a remote tracking facility. The 6555th's Satellite
Systems Division was responsible for the RVCF.
C-31
As we noted earlier, Core Vehicle C-31 was placed in storage in Cell
#3 of the VIB on 6 December 1976. It was moved to Cell #4 and erected on
Transporter #3 on 2 June 1977, and then it was moved to the SMAB on June
3rd. The core vehicle and solid rocket motors were mated a few days later,
and Launch Vehicle C-31 was moved out to Complex 40 on June 16th. The vehicle
remained at Complex 40 for ten weeks to support a scheduled mission, which,
unfortunately, did not materialize. The vehicle was returned to the SMAB
on 6 September 1977, and the solid rockets were demated from the core.
Core Vehicle C-31 returned to Cell #3 for storage on September 19th. The
core was retested in Cell #2 toward the end of September, and it was put
back in storage in Cell #3 on 8 October 1977. Interestingly enough, the
vehicle's transtage (Stage III) had been used for a shock test at the Arnold
Engineering Center in Tennessee, but it had been refurbished for flight
prior to its arrival at the Cape in June 1976. The transtage had been flight-worthy
in the summer of 1977, but the extended wait in storage began to take its
toll: a crack in one of the transtage's longerons was noticed on 21 February
1978, and soon more cracks and soft aluminum patches were discovered. A
decision was made to replace the transtage's control module entirely, and
the transtage was shipped back to Martin Marietta's plant in Denver on
29 August 1978 to have the work done. The transtage was repaired, and it
was returned to the Cape on 8 January 1979. Core Vehicle C-31 was moved
out of storage on 16 January 1979, and it was transferred to Cell #2 of
the VIB for reacceptance testing. The Reacceptance CST was completed successfully
on March 9th, and the core vehicle was moved to the SMAB for its solid
rocket mate on 14 March 1979.
Launch Vehicle C-37
The Space Division history for FY 1980 notes only two significant problems
with C-37: 1) replacement of the vehicle's Stage I hydraulic pump during
acceptance testing and 2) a battery malfunction five days before launch.
unscheduled five-minute
hold
The hold was called to allow the contractor time to complete his electrical
instrumentation checkout of the launch vehicle's third stage.
IUS Pathfinder
Test Vehicle (PTV-C)
The PTV-C had arrived at the SMAB on 21 July 1981, and it completed
its processing there on 7 January 1982.
operational IUS
The first operational IUS (IUS-1) was assigned to NASA's Tracking and
Data Relay System satellite (TDRS-A), which was scheduled for launch on
Challenger's maiden flight (i.e., the sixth Shuttle flight in the program).
IUS-2 was launched on 30 October 1982, and IUS-1 was launched later, on
4 April 1983. As a point of interest, IUS-1 completed its acceptance testing
on 22 May 1982, and it was moved to the SMAB on July 19th. After processing
was completed at the SMAB, IUS-1 was moved to NASA's Vertical Processing
Facility (VPF) on Merritt Island on November 8th. The IUS was mated to
the TDRS-A satellite at the VPF on 24 November 1982. The IUS and spacecraft
were installed in the orbiter's cargo bay on 24 February 1983. Following
Challenger's launch on 4 April 1983, IUS-1 and the TDRS-A satellite were
spring-ejected from the orbiter's cargo bay about ten hours into the mission.
Though the IUS' first stage "burn" went well, the second stage's
rocket nozzle malfunctioned during the second stage burn. The Air Force
Satellite Control Facility in California and a ground control station at
White Sands, New Mexico managed to separate the IUS from the spacecraft,
but the second stage burn was cut off early. Several months of altitude
correction were required before the TDRS-A reached the proper geosynchronous
orbit and entered normal service.
DSCS II/III payload
The payload consisted of two DSCS satellites: one operational DSCS
II communications satellite and the first flight model DSCS III satellite.
(Author's note: a contract for full-scale development of the DSCS III had
been awarded to General Electric in 1977. Under that contract, GE agreed
to build and test one qualification model of the DSCS III satellite and
deliver two flight models of the satellite. The company also agreed to
build two engineering models of the electronic equipment, computer programs
and communications hardware that would be needed to control the satellites
from the ground.) The operational DSCS II satellite was nine feet in diameter
and nine feet long. It weighed approximately 1,350 pounds. The DSCS III
satellite measured 6 x 6 x 7 feet. In its operational configuration, the
DSCS III weighed approximately 2,500 pounds.
Greenwich Mean Time
Mission-related times were presented in Greenwich Mean Time (GMT) in
1982 and later-year ESMC and 45th Space Wing histories to avoid the confusion
inherent in Eastern Daylight Time and Eastern Standard Time references.
The Air Force specified Greenwich Mean Time with a "Z" (Zulu)
suffix. The "Z" designation will be used for all times appearing
in the remainder of this chapter.
transtage
The TITAN 34D Program Requirements Document was revised in early 1982
to allow the transition of classified payloads from TITAN IIICs to TITAN
34Ds equipped with transtages (TSs) as well as IUSs. The transtages were
required due to slips in the IUS program schedule.
launch operations
ground to a halt
As we noted in Chapter I, the TITAN 34D-9 launch disaster at Vandenberg
AFB on 18 April 1986 effectively grounded TITAN 34D launch operations on
both coasts until an aggressive recovery program was implemented to reconfirm
the TITAN 34D's reliability.
D-13's acceptance testing
Core Vehicle D-13 was moved from Cell #1 to Cell #2 after Core Vehicle
D-11 was moved from the VIB to the SMAB in February 1984. D-13's first
stage was replaced in Cell #2, and the vehicle was moved back to Cell #1
for acceptance testing.
Under the command
Colonel Martinelli assumed command of the 6555th on 25 February 1985.
His predecessor, Colonel Charles A. Kuhlman, commanded the Test Group for
one of the longest periods on record (10 August 1981 through 24 February
1985). Colonel Kuhlman's predecessor was Colonel Walter S. Yager, who succeeded
Colonel George L. Rosenhauer as Test Group Commander on 28 February 1980.
NDT facility
The facility consisted of three cells-A, B and C. Cells A and B were
identical 20 x 32-foot reinforced concrete rooms with removable roof panels
which allowed rocket motors to be lowered into the cells. Cell C was built
the same way, but its floorspace was considerably larger (e.g., 47 x 58
feet). A central control area joined cells A and B in one wing of the facility
with Cell C in the other wing. Together with its environmental enclosure
and 85-ton crane, the facility cost approximately $27.8 million to build
and equip.
refurbish Launch Complex
41
Complex 41 had been deactivated at the end of 1977 after NASA's last
VOYAGER mission was launched to the outer planets. For the next eight years,
the Cape's corrosive salt air environment ate away at the site unchecked.
Under the circumstances, Complex 41's renovation had to be extensive. The
project included: 1) tearing out or modifying structural, mechanical and
electrical systems, 2) sandblasting, priming and painting Complex 41's
towers, 3) changing fuel systems and 4) installing air pollution control
devices on fuel and oxidizer systems. Though Martin Marietta was responsible
for the project, the Eastern Space and Missile Center formed a TITAN IV
Site Activation Working Group (SAWG) to monitor the project's progress.
The Test Group and various ESMC agencies (e.g., contracts, quality assurance,
range facilities engineering, range systems development, safety, range
contractors, ETR program management and the Aerospace Corporation) sent
representatives to the SAWG's monthly meetings.
corrosion was discovered
In the fall of 1987, signs of corrosion were detected under the UT's
new paint job. Some corrosion was also discovered on a propellant piping
chase in May 1988, but a preliminary propellant "hot flow" review
in September 1988 confirmed the integrity of Complex 41's fueling system.
After the first TITAN IV launch in June 1989, it was apparent that some
portions of the towers would have to be sandblasted, primed and painted
all over again. At the end of July 1989, the Test Group asked Range Facilities
Engineering to task the Launch Base Services contractor to reaccomplish
the work. Pan American's remedial work was accomplished in the summer of
1990.
CENTAUR
Payload Operations Control Center (CPOCC)
The CPOCC was originally designed to control and monitor CENTAUR vehicle,
spacecraft and support systems operations for Shuttle/CENTAUR missions.
The facility was linked to spacecraft/CENTAUR integration at the SPIF and
Shuttle/CENTAUR systems at NASA's Vertical Processing Facility on Merritt
Island. It was also linked to ATLAS/CENTAUR integration and testing systems
on Launch Complex 36.
second floor redesigned
Sterns-Roger was contracted to redesign and modify the second floor
to provide Test Group and higher headquarters commanders and managers with
information displays and communications outlets to their agencies. The
modifications included new walls, LMCC consoles, fire suppression and air-conditioning
systems, new cable raceways and consoles for the Command Management Control
Center (CMCC). The work was completed in December 1988. The LMCC was activated
in July 1989, and it was fully operational in the spring of 1990.
three alternatives
The three alternatives were: 1) modify the existing SMAB, 2) build
a duplicate of the old SMAB, and 3) build an improved SMAB (i.e., the SMARF).
A new improved SMAB would cost more to build than modifications to the
old SMAB, but (surprisingly) it would be cheaper to build than a duplicate
of the old SMAB. A persuasive point in favor of the SMARF was that it could
be designed to allow the stacking and storage of two flight sets of SRMUs
in a vertical, checked out configuration, thereby optimizing the operators'
ability to return a TITAN IV to the SMARF if a problem developed at the
launch pad. (Author's note: though the basic TITAN IV vehicle was designed
to carry two seven-segment solid rocket motors, the new three-segment SRMU
design was expected to be introduced once TITAN IV operations were underway.
Each of the SRMU segments would measure 12 x 30 feet, as opposed to the
seven 10 x 10-foot motor segments carried on the basic TITAN IV vehicle.
Consequently, an SRMU stack was significantly taller and heavier than a
basic seven-segment SRM stack, and it posed a bigger storage problem. Both
types of solid rocket motors would continue to be used with the TITAN IVs,
but the SRMUs would be used for heavier payloads and/or higher energy orbits.)
contract
Modifications to the contract raised its value to more than $42 million
before the SMARF was completed in October 1991.
launch vehicle (D-8)
Core Vehicle D-8 arrived at the Cape on 19 February 1985. It was erected
on Transporter #2 in Cell #1 of the VIB by February 27th, and its Acceptance
CST was completed there on 7 May 1985. The vehicle was transported to the
SMAB for solid rocket mating on July 15th. As luck would have it, a severe
thunderstorm developed near the SMAB on July 16th, and a lightning strike
evidently damaged some of D-8's guidance system components. The damage
was discovered after Launch Vehicle D-8 was moved to Complex 40, but Baseline
CSTs at the pad were completed successfully at the end of August 1985 after
the components were repaired or replaced. In the meantime, news of the
TITAN 34D-7 failure at Vandenberg prompted a complete reassessment of D-8's
propulsion systems, and that new requirement delayed the launch by at least
several months. A second Baseline CST was completed on D-8 on 28 February
1986, but the vehicle had to be returned to the VIB for a thorough solid
rocket motor inspection in July 1986 after the TITAN 34D-9 launch failure
in April grounded the TITAN fleet. A Reassessment CST was completed on
D-8 in the VIB on 27 May 1987, and the core vehicle was moved to the SMAB
for another solid rocket mate on July 8th. Launch Vehicle D-8 was moved
out to Complex 40 on July 10th, and a third Baseline CST was required as
a retest for extensive "black box" (avionics) replacements and
other improvements. Final preparations for the November 1987 launch continued
in a relatively routine fashion through the summer and early fall of 1987.
unscheduled holds
The first unscheduled hold occurred at T minus 10 minutes when vessels
were detected in the launch danger zone. A 29-minute delay in the countdown
was required to get the intruders to safety. The second unscheduled hold
was called at T minus five minutes when the umbilical retract mechanism
on Solid Rocket Motor #1 failed to lock. A technician was sent out to the
pad to lock the mechanism manually, and the hold was terminated after 69
minutes.
beginning of the TITAN
IV era
The first TITAN IV liquid rocket engines arrived at the Cape on 18
December 1987, and the roll-out ceremony for stages I and II of the TITAN
IV pathfinder vehicle took place at Complex 41 on 14 January 1988. Colonel
Bourne succeeded Colonel Dominick R. Martinelli as Test Group Commander
on 15 January 1988. As noted earlier, Colonel Michael R. Spence assumed
command of the 6555th Aerospace Test Group on 2 October 1990, and he succeeded
Colonel Bourne.
countdown
Only one nine-minute unscheduled hold was required at L minus five
minutes to clear the launch danger area. The countdown proceeded smoothly
thereafter.
ATLAS I/CENTAUR
upper stage flight failures
Both of the failures involved commercial ATLAS I/CENTAUR vehicles launched
from Launch Complex 36B on the Cape. The first failure occurred on 18 April
1991 when one of the CENTAUR's Pratt & Whitney engines failed to start
about six minutes after lift-off. Range Safety sent destruct commands,
and the vehicle's destruction was confirmed seconds later. The second failure
occurred on 22 August 1992. The flight on that date went well until the
CENTAUR upper stage malfunctioned, and Flight Control Officers (FCOs) had
to destroy the vehicle about eight minutes after launch.
Lt. Colonel George
L. Rosenhauer
Lt. Colonel Rosenhauer assumed the position of STS Division Chief on
4 August 1975.
Chief of the STS Division
Lt. Colonel Charles A. Kuhlman assumed the post of Assistant Chief,
STS Division on 10 July 1978. He succeeded Lt. Colonel Green as STS Division
Chief in 1979.
transferred
The transfer raised the Division's assigned strength to ten officers
and one civilian on 1 October 1977. Eleven officers and one civilian were
assigned to the Division by the end of 1977.
IUS was mission-specific
The Space and Missile Systems Center (SMC) in Los Angeles provided
overall program management for the IUS, and Boeing Aerospace was SMC's
prime contractor for IUS operations. During the period in question, the
6555th Aerospace Test Group served as the "on-scene" launch support
agency for Shuttle/IUS operations at KSC and the Cape. The 45th Operations
Group's Launch Vehicle Directorate also contributed to the effort after
the 45th Space Wing was activated on 12 November 1991.
support an astronaut bailout
One HC-130 aircraft was on cockpit alert at Patrick. One KC-130 was
on ready alert at Cherry Point, North Carolina, and two E-2C Hawkeyes were
on ready alert at the Naval Air Station in Norfolk, Virginia. One Coast
Guard cutter (with helicopter) was stationed about 100 nautical miles downrange,
and one Navy ship (with helicopter) was positioned 150 nautical miles downrange.
An HC-130 aircraft orbited about 175 nautical miles downrange, and C-130s
were on cockpit alert at Moron Air Base (Spain), Banjul (the Gambia), Zaragoza
(Spain) and Ben Guerir (Morocco). Two P-3C aircraft were also on ready
alert at Jacksonville, Florida and at Lajes in the Azores. Two H-60 Army
medical evacuation helicopters and four H-1 support helicopters were also
on alert at Edwards Air Force Base, California to handle medical, security
and photographic support tasks.
orbiter's three main engines
The solids produced 2,650,000 pounds of thrust apiece, and each of
the orbiter's main engines produced 390,000 pounds of thrust at sea level.
At altitude, each main engine's performance increased to approximately
488,000 pounds of thrust.
SYNCOM IV
As we noted earlier, the SYNCOM IV constellation was sent into space
to replace aging FLTSATCOM satellites that provided worldwide defense communications
for submarines and ships at sea. The SYNCOM IV was a Hughes HS381 satellite
with a life expectancy of ten years. In its stowed configuration, the satellite
measured 14 feet 1 inch by 13 feet 9 inches. It weighed 17,081 pounds.
The satellite was deployed horizontally by means of a rotational pivot.
The SYNCOM IV was pushed off the port side of the Shuttle's cargo bay at
a velocity of 1.4 feet per second. The satellite's perigee kick motor (e.g.,
a MINUTEMAN III TU-882 upper stage) fired 45 minutes later, injecting the
payload into an elliptical transfer orbit. Subsequently, a liquid apogee
motor circularized the SYNCOM IV's orbit at an altitude of 19,300 nautical
miles and established final synchronous orbit.
all-military Shuttle mission
The term "all-military Shuttle mission" refers only to the
major payload or payloads carried into space, not the composition of the
crew. Civilians were not excluded from crew duty, and a civilian crewmember
(Dr. Kathryn C. Thornton) served on an all-military mission in November
1989.
two unscheduled holds
The first hold was called at 1255Z after a cargo vessel was detected
in the surveillance area. The second unscheduled hold was called at 1305Z
for foul weather, and it lasted 45 minutes.
Shuttle
mission at 0750:22Z on 28 February 1990
The mission experienced a total of five launch delays and scrubs between
February 21st and February 28th. The launch was slipped 24 hours due to
a crew member illness on February 21st. A forecast of poor weather (compounded
by uncertainty concerning the crew member's health) pushed the launch to
February 24th. The countdown on the 24th was scrubbed at L minus 15 hours
due to weather constraints, and another launch attempt on February 25th
was scrubbed at T minus 31 seconds when the Eastern Range's Cyber B computer
failed. The countdown on February 26th was scrubbed due to high upper level
winds, but the final countdown on February 28th was successful despite
unscheduled holds for weather in the launch area.
Shuttle Pallet Satellite
II
The Shuttle Pallet Satellite II (SPAS II) was an advanced version of
the SPAS I spacecraft that flew on two civilian Shuttle missions in June
1983 and April 1984. The Shuttle's Remote Manipulator System (RMS) deployed
the satellite. Once the SPAS II's altitude control system was checked out,
Discovery maneuvered about ten kilometers away from the spacecraft. At
that distance, the SPAS II took "far-field" measurements of the
Shuttle's OMS and primary control system exhaust plumes to characterize
their spectral and radiometric signatures. Similar observations and measurements
were made of Earth and Earthlimb fields to provide a background model for
boost detection and target tracking purposes. Following the far-field measurements,
Discovery moved to a distance of about 2.25 kilometers to let the SPAS
II capture near-field measurements. A rendezvous followed, and the RMS
grappled the SPAS II and brought it aboard. The three Chemical Release
Observation (CRO) sub-satellites were also carried aboard Discovery in
get-away special canisters. The CRO sub-satellites were ejected into space,
and they were commanded to release three different rocket fuel clouds (e.g.,
monomethyl hydrazine, unsymmetrical dymethylhydrazine and nitrogen tetroxide)
for observation by the IBSS and other instruments during the mission.
end of 1959
The Air Force Ballistic Missile Division supported a total of ten Air
Force-sponsored THOR-ABLE, THOR-ABLE I and THOR-ABLE II space launches
from Pad 17A before the end of 1959.